Trayed Column – Flooding Due to a Mechanical Obstruction

Pre Job Info:

The client was unable to meet their product specifications, and there were indications of liquid being carried overhead. The client suspected either foaming or flooding. There was no reliable pressure differential available for the tower.

TowerScan Results:

The scan revealed the tower to be flooded from tray 12 upwards. The sharpness of the transition from a flooded condition to a normally operating tower above and below tray 12 indicated an obstruction in the tray 12 downcomer. As the tower had a history of solids (salts) building up on the trays, the customer performed a water wash of the tower, after which the tower’s operation returned to normal.

Download

Get Started

There is no better time to get TowerScan to quote on your scanning needs. Our expert staff are standing by to help you.

Here is all you need to get started:
  1. An evaluation of your immediate concerns and an idea of what you wish to accomplish.
  2. An overall mechanical drawing of the tower or process equipment. This tells us things like tower height and diameter, as well as the elevation and orientation of trays, packed beds and nozzles.
  3. Access to the top of your tower.
  4. A safe work permit.
Enter Your Details
  • Drop files here or